Project Results

1. Construction of 6 combined heat and power biogas facilities

After finalization of the selected projects the total installed capacity of biogas CHP facilities in Serbia will be increased for 130%

INVESTORINSTALLED CAPACITY (MW) INVESTMENT VALUE (USD)
1Forkom doo, Beograd0,20 1,42 mil
2BGS gama BP doo, Bač0,65 2,14 mil
3BGS beta BP doo, Bač0,65 2,14 mil
4BGS alfa BP doo, Bač0,65 2,14 mil
5Biogas Energy doo, Alibunar3,57 12,43 mil
6Bioelektra doo, Zrenjanin0,602,37 mil
TOTAL6,3222,66 mil

 

pic1pic2

pic3

 

 

 

 

 

 

 

 

Alibunar

INVESTOR (COMPANY)Biogas Energy doo, Alibunar
INSTALLED POWER CAPACITY 3.57 MWel
INSTALLED THERMAL CAPACITY 3.20 MWth
INVESTMENT VALUE12.43 mil USD
TOTAL EFFICIENCY83.3 %
GRANT275,000 USD
BIOMASS FEEDSTOCK25.156 t/year Corn and sorghum silage, wheat straw, waste from starch plant and pig manure
MATERIAL OUTPUTUp to 20.000 t/year, of solid fertilizer and up to 50.000 t/year of liquid fertilizer

 

picB

 

Bač

INVESTORS (COMPANIES)1. BGS Alfa BP doo, Bač 2. BGS Beta BP doo, Bač 3. BGS Gamma BP doo, Bač
INSTALLED POWER CAPACITY 3 x 0.65 MW = 1.95 MWel
INSTALLED THERMAL CAPACITY 3 x 0.70 = 2.10 MWth
INVESTMENT VALUE 3 x 2.14 mil USD = 6.42 mil USD
TOTAL EFFICIENCY81.6 %
GRANT3 x 275,000 USD = 826,500 USD
BIOMASS FEEDSTOCK23.056 t/year Sugar beat residues, sorghum silage, cattle manure, sheep manure and fruit and vegetable residues
MATERIAL OUTPUT2880 t/year, agri-pelet

 

picD

 

Zrenjanin 

INVESTOR (COMPANY)Bioelektra doo, Zrenjanin
INSTALLED POWER CAPACITY 0.60 MWel
INSTALLED THERMAL CAPACITY 0.60 MWth
INVESTMENT VALUE2.37 mil USD
TOTAL EFFICIENCY82 %
GRANT275,500 USD
BIOMASS FEEDSTOCK4.014 t/year Sugar beat cuts, sugar production waste and corn silage
MATERIAL OUTPUT4.000 t/year, fertilizer

 

picE

Aleksinac

INVESTOR (COMPANY)Forkom doo, Beograd (plant located in Aleksinac)
INSTALLED POWER CAPACITY 0.20 MWel
INSTALLED THERMAL CAPACITY 0.18 MWth
INVESTMENT VALUE1.42 mil USD
TOTAL EFFICIENCY84 %
GRANT (USD)222,200 USD
BIOMASS FEEDSTOCK3.118 t/year Sorghum residues, corn residues, poultry manure and cattle manure
MATERIAL OUTPUT2.494 t/year, fertilizer

picF

 

2. Instruments for ensuring financial sustainability of investments in biomass fired plants: model contracts for long term biomass supply along with elaborate technical biomass catalogues

 

vodic

 

 

3. Six bilingual guides for investors in renewable energy plants

 

vodici

 

 

4. The Social Cost-Benefit Analysis for each of six biogas CHP plants supported by the Project according to standard European Commission methodology for investment projects. 6 bilingual documents.

COST BENEFIT ANALIZE

5, Analysis of barriers to construction of biogas/biomass CHP plants in Serbia. Bilingual document.

TEHNICKE BARIJERE

 

6. Analysis of barriers to financing biogas CHP plants in Serbia. Bilingual document.

FINANSIJSKE BARIJERE

7. Methodology and model report for reporting of privileged power producer from biomass/biogas plants to Ministry of Mining and Energy in line with Decree on the requirements and procedure of acquiring the status of privileged power producer, preliminary privileged power producer and power producer from renewable energy (Official Gazette of the Republic of Serbia No. 56/2016)

ENGL METODOLOGIJA

8. Short rotation energy crops of fast-growing tree species in Serbia: biomass production, legislation, market, and environmental impacts – potentials and constraints

ENGL ENERGETSKI ZASADI

9. Opportunities for growing short-rotation energy crops in agricultural land in the Republic of Serbia 

ENGL ZEMLJISTE

10. UNDP Position paper: Status of Using Wood Biomass for Energy Purposes in Serbia

ENGL POSITION PAPER DRVNA BIOMASA