• DSC_1270
  • DSC_1310
  • http://wowslider.com/
  • DSC_1336
1 2 3 4 5 6 DSC_12707 DSC_13108 DSC_13249 DSC_133610
wow slider by WOWSlider.com v8.6




Project Results

1. Construction of 6 combined heat and power biogas facilities

After finalization of the selected projects the total installed capacity of biogas CHP facilities in Serbia will be increased for 130%

INVESTORINSTALLED CAPACITY (MW) INVESTMENT VALUE (USD)
1Forkom doo, Beograd0,20 1,42 mil
2BGS gama BP doo, Bač0,65 2,14 mil
3BGS beta BP doo, Bač0,65 2,14 mil
4BGS alfa BP doo, Bač0,65 2,14 mil
5Biogas Energy doo, Alibunar3,57 12,43 mil
6Bioelektra doo, Zrenjanin0,602,37 mil
TOTAL6,3222,66 mil

 

pic1pic2

pic3

 

 

 

 

 

 

 

 

Alibunar

INVESTOR (COMPANY)Biogas Energy doo, Alibunar
INSTALLED POWER CAPACITY 3.57 MWel
INSTALLED THERMAL CAPACITY 3.20 MWth
INVESTMENT VALUE12.43 mil USD
TOTAL EFFICIENCY83.3 %
GRANT275,000 USD
BIOMASS FEEDSTOCK25.156 t/year Corn and sorghum silage, wheat straw, waste from starch plant and pig manure
MATERIAL OUTPUTUp to 20.000 t/year, of solid fertilizer and up to 50.000 t/year of liquid fertilizer

 

picB

 

Bač

INVESTORS (COMPANIES)1. BGS Alfa BP doo, Bač 2. BGS Beta BP doo, Bač 3. BGS Gamma BP doo, Bač
INSTALLED POWER CAPACITY 3 x 0.65 MW = 1.95 MWel
INSTALLED THERMAL CAPACITY 3 x 0.70 = 2.10 MWth
INVESTMENT VALUE 3 x 2.14 mil USD = 6.42 mil USD
TOTAL EFFICIENCY81.6 %
GRANT3 x 275,000 USD = 826,500 USD
BIOMASS FEEDSTOCK23.056 t/year Sugar beat residues, sorghum silage, cattle manure, sheep manure and fruit and vegetable residues
MATERIAL OUTPUT2880 t/year, agri-pelet

 

picD

 

Zrenjanin 

INVESTOR (COMPANY)Bioelektra doo, Zrenjanin
INSTALLED POWER CAPACITY 0.60 MWel
INSTALLED THERMAL CAPACITY 0.60 MWth
INVESTMENT VALUE2.37 mil USD
TOTAL EFFICIENCY82 %
GRANT275,500 USD
BIOMASS FEEDSTOCK4.014 t/year Sugar beat cuts, sugar production waste and corn silage
MATERIAL OUTPUT4.000 t/year, fertilizer

 

picE

Aleksinac

INVESTOR (COMPANY)Forkom doo, Beograd (plant located in Aleksinac)
INSTALLED POWER CAPACITY 0.20 MWel
INSTALLED THERMAL CAPACITY 0.18 MWth
INVESTMENT VALUE1.42 mil USD
TOTAL EFFICIENCY84 %
GRANT (USD)222,200 USD
BIOMASS FEEDSTOCK3.118 t/year Sorghum residues, corn residues, poultry manure and cattle manure
MATERIAL OUTPUT2.494 t/year, fertilizer

picF

 

2. Instruments for ensuring financial sustainability of investments in biomass fired plants: model contracts for long term biomass supply along with elaborate technical biomass catalogues

 

vodic

3. Six bilingual guides for investors in renewable energy plants

 

vodici